SITE SURVEY – GIS/VA1 CONTROL CABINET – TUBING INSTALL AND TESTING – COMISSIONING

For this project we carried out a detailed site survey to assist in the design of a site upgrade. During this survey it was determined that the existing actuator was still fit for purpose. The actuator was then overhauled in our works and the valve telemetry was replaced with a new Westlock switchbox.

A new GIS/VA1 control cabinet was designed and built to meet our customer specific needs. Our service technicians carry out the on site actuator install to the buried duty valve as well as installing and testing the instrument tubing. Once all the tubing had been re-instated a full pressure gas test was carried out for commissioning on the entire valve, actuator and controls package.

Power Mechanical’s VA1 control cabinets have an established track record of over 25 years in service.