In October 2024, our Great Yarmouth team designed and manufactured a bespoke Hydraulic Power Unit. After a successful factory acceptance test in the presence of our client, we delivered the Hydraulic Power Unit to site ready to commence the offshore phase of the project.
In readiness for the offshore work scope we prepared and delivered hire equipment consisting of Pressure Test Equipment, Pigging Equipment and Pre-Charge Equipment to our client’s port facility. Our experienced technicians mobilised to the 27H offshore platform in December 2024 to commence the installation of two Hydraulic Power Units, small bore instrument tubing installation, pressure testing, pigging and accumulator pre-charging.
Commissioning was completed during January 2025 and the two Hydraulic Power Units are ready for the injection test to commence.