Completed Project

Our technicians completed a project for one of our customers in the gas distribution network.

Scope of Works: Remove the existing obsolete actuators and install manual gearboxes as part of a larger scope of site improvements and upgrades.

Works Carried Out: Our technicians were mobilised to site to remove the existing actuators from the valves to take detailed measurements of the valve topworks and the stem extension heights to ensure the gearboxes are at a good operable height.

Working with our suppliers we provided general arrangement drawings of the proposed solution for our customers approval. The design was approved and gearboxes were sized then procured.

Once site upgrade works had commenced our technicians returned to site to fit and commission the new gearboxes, ensuring everything was fully operational before handing the equipment back to the customer. A great example of Power Mechanical’s hands-on engineering and teamwork delivering practical, reliable solutions for our clients.